Payment Schedule


Sr. no.
Payment Scheduled 3 Bhk
Percent
1
At the time of booking (with allotment letter)
15%
2
At the time of agreement
10%
3
On or before completion of Plinth
10%
4
On or before completion 2nd Roof slab
10%
5
On or before completed of 4th Roof slab
10%
6
On or before completed of 7th Roof slab
10%
7
On or before Finishing of flats
30%
8
Before possesion of 1 month
5%
9
Full & final payment before the position (if any)
Total :-
100%

 

Sr. no.
Payment Scheduled 2 Bhk
Percent
1
At the time of booking (with allotment letter)
15%
2
At the time of agreement
10%
3
On or before completion of Plinth
10%
4
On or before completion 1st Roof slab
10%
5
On or before completed of 3rd Roof slab
10%
6
On or before completed of 5th Roof slab
10%
7
On or before Finishing of flats
30%
8
Before possesion of 1 month
5%
9
Full & final payment before the position (if any)
Total :-
100%

 

Sr. no.
Payment Scheduled 3/4 Bhk
Percent
1
At the time of booking (with allotment letter)
15%
2
At the time of agreement
10%
3
On or before completion of Plinth
10%
4
On or before completion 1st Roof slab
10%
5
On or before completed of 2nd Roof slab
10%
6
On or before completed of 3rd Roof slab
10%
7
On or before completed of 4th Roof slab
10%
8
On or before Finishing of flats
20%
9
Before possesion of 1 month
5%
10
Full & final payment before the position (if any)
Total :-
100%